DCM Erectors, Inc.

Installers of structural steel for new grass roots/
refurbished structures and transportation projects.

 


New from THE DAVIS GROUP:

Internal Climbing Tower Crane. Click here for video

On Track at Columbia University Click here for video



NEW YORK TIMES TOWER

 

With major steel work completed early in 2007, The New York Times Tower rises 52 stories and is surmounted by a spire that brings the building's total height to 1,142 feet, exceeding the height of the Chrysler Building. Both the steel frame and the spire have been erected by DCM. One of the most important buildings to be built on the Eighth Avenue since World War II, the new Times headquarters is a sleek addition to the midtown theatre district, next to the New York Port Authority Terminal.

 

 

 


COMPLETED: Bloomberg Tower (2004)

 

THE BLOOMBERG TOWER

The $450 million Bloomberg building, cited for an ENR “Project of the Year” award in 2004, houses the new headquarters of Bloomberg LP and its nearly 4,000 employees. The 55-story tower features 105 luxury condos with views of Central Park and an additional 180,000 sq. ft. of office and retail space. DCM kept the project on track by starting fabrication for initial phases while final designs were progressing.

 

 


COMPLETED: Time Warner (2003)

 

The Time Warner Center: Completed 2003

This landmark skyscraper at Columbus Circle in Manhattan, completed at a cost of $1,700,000,000.00, is the most expensive building ever erected in New York. It consists of two 750 ft residential towers and a steel " podium" by DCM. The curved base houses CNN studios, shops and a theater for Jazz.

 

 

 

 


LESTER B. PEARSON INTERNATIONAL AIRPORT, Toronto, ON

DCM Canada:

77 Bellfield Rd.m Suite 100
Toronto, Canada, M9W166

Phone: (416) 241 - 6967
Fax: (416) 241 - 3231

 

 

 


Steel Erection and Modification in Phases as shown Below:



Erected under an existing roof
 

Intermediate Steel Levels I, II & III (7,000 ton)
The Intermediate Steel involved the erection of new floor and bracing members under an existing roof structure resulting in close quarter work requiring precise sequencing and thorough coordination with civil and finishing trades. DCM Erectors' provision of Work Around Solutions to access and trade conflicts enabled the Construction Manager to achieve the benefits of their unorthodox and high-risk construction schedule. The required Customer Changes necessary to achieve occupancy were handled expeditiously in the field thereby greatly assisting the Construction Manager in the maintenance of the planned schedule.

 



Complicated Pick
 

Liner Steel & Apron Tower (9,500 ton)
The Liner Steel & Apron Tower contract included the erection of a portion of the New Terminal Building that would eventually become the Departure Lounges, Security and Baggage Handling facilities. The construction of the Apron Tower, eventually housing the Ground Traffic Control Operations, consisted of six full floor lifts that were assembled off site and transported to the erection position during Windows of Opportunity in the Air Traffic Operations. The installation of Architecturally Exposed Structural Steel (AESS) formed a significant portion of the Liner Steel Contract.




Need many pieces
to make 1,000 tons
 

Canopy Steel & Level III Reinforcing (1,000 ton)
The reinforcing of the existing 3rd Floor amidst the intense finishing trades activities required all of DCM Erectors logistical and coordination ability in order to help the GTAA Construction Management team meet its schedule goals. Erection of the Kiosk and Canopy Steel over and around finished Terrazzo Floors required elaborate rigging and welding techniques. The final product, predominantly Architectural Exposed Structural Steel, eloquently proves DCM Erectors capabilities in the Miscellaneousl and High End Ornamental Steel arena.

For more infomation click here to see complete project list.